There will be resurfacing works on the A75, near Lochfoot from the end of this week, with the A75 being closed over the weekend. There will be a diversion via Haugh of Urr and Dalbeattie.
The programme of work is as follows:
- From 8pm on Friday 28th March until 6am on Monday 31st March, a full weekend closure will be in place.
- From Monday 31st March until Thursday 3rd April, there will be overnight closures at this location during the hours of 8pm and 6am, each night.
- Traffic management will be removed by 6am on Friday 4th April.